Progress Details Report

LGFS Huts at Gaurikund
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 8067000.006140434.77
2 Site Development in (Job) 1.001.00
3 Foundation and Plinth Work in (Job) 1.001.00
4 Structural Frame in (Job) 1.001.00
5 Doors & Windows in (Job) 1.001.00
6 Water Supply and Sanitary work in (Job) 1.001.00
7 Electrification Works in (Job) 1.001.00
8 Other Allied Works & Finishing Work in (Job) 1.000.50
9 Furnishing Work in (Job) 1.001.00
10 Quality in (%) 95