Progress Details Report

Hybrid Huts at Deval
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 9224000.001650632.00
2 Site Development in (Job) 1.000.70
3 Foundation and Plinth Work in (Job) 1.001.00
4 Structural Frame in (Job) 1.000.90
5 Doors & Windows in (Job) 1.000.70
6 Water Supply and Sanitary work in (Job) 1.000.00
7 Electrification Works in (Job) 1.000.00
8 Other Allied Works & Finishing Work in (Job) 1.000.20
9 Furnishing Work in (Job) 1.000.00
10 Quality in (%) 94.04