Progress Details Report

Hybrid Huts at Barkot
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 7377000.000.00
2 Site Development in (Job) 1.001.00
3 Foundation and Plinth Work in (Job) 1.001.00
4 Structural Frame in (Job) 1.001.00
5 Doors & Windows in (Job) 1.001.00
6 Water Supply and Sanitary work in (Job) 1.001.00
7 Electrification Works in (Job) 1.001.00
8 Other Allied Works & Finishing Work in (Job) 1.001.00
9 Furnishing Work in (Job) 1.001.00
10 Quality in (%) 90.75