Progress Details Report

Nathuwakhan-Suyalbari
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 19800000.0017135996.00
2 Hill side Cutting & Slip clearence in (KM) 0.440.44
3 R/Wall, B/ Wall Type Protection works in (m) 225.00225.00
4 G-2 in (KM) 0.000.00
5 G-3 in (KM) 0.900.90
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 10.1010.10
7 Cause Way in (No) 2.002.00
8 Culverts/Scupper in (No) 104.00104.00
9 longitudinal Drain in (m) 13000.0013000.00
10 Quality in (%) 85