Progress Details Report

Nainital-Kaladhungi- Bajpur Doraha Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 57075000.0054687362.00
2 Hill side Cutting & Slip clearence in (KM) 0.340.34
3 R/Wall, B/ Wall Type Protection works in (m) 2773.002773.00
4 BM i/c Prime Coat, Tack Coat in (KM) 0.830.83
5 SDBC i/c Tackcoat in (KM) 15.5515.55
6 Cause Way in (No) 4.004.00
7 Culverts/Scupper in (No) 5.005.00
8 longitudinal Drain in (m) 15580.0015580.00
9 Road Furniture in (No) 136.00136.00
10 Quality in (%) 90