Progress Details Report

Dwarahat-Binta Someshwar Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 267296000.0081527261.01
2 Hill side Cutting & Slip clearence in (KM) 3.003.00
3 R/Wall, B/ Wall Type Protection works in (m) 1300.001300.00
4 G-3 in (KM) 0.160.16
5 BM i/c Prime Coat, Tack Coat in (KM) 8.008.00
6 SDBC i/c Tackcoat in (KM) 12.0012.00
7 Cause Way in (No) 3.003.00
8 Culverts/Scupper in (No) 6.006.00
9 longitudinal Drain in (m) 12010.0012010.00
10 Crash Barrier in (m) 0.930.93
11 Parapet in (No) 876.00876.00
12 Road Furniture in (No) 35.0035.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 88.63