1 |
Expenditure in (Rs.) |
32000000.00 | 31747632.00 |
2 |
Hill side Cutting & Slip clearence in (KM) |
3.67 | 3.67 |
3 |
R/Wall, B/ Wall Type Protection works in (m) |
200.00 | 200.00 |
4 |
GSB/RBI/G-1 in (KM) |
3.65 | 3.65 |
5 |
G-2 in (KM) |
3.65 | 3.65 |
6 |
G-3 in (KM) |
3.65 | 3.65 |
7 |
PC/CC i/c Prime Coat, Tack Coat in (KM) |
3.67 | 3.67 |
8 |
BM i/c Prime Coat, Tack Coat in (KM) |
0.20 | 0.20 |
9 |
SDBC i/c Tackcoat in (KM) |
2.00 | 2.00 |
10 |
Culverts/Scupper in (No) |
3.00 | 3.00 |
11 |
longitudinal Drain in (m) |
3643.75 | 3643.75 |
12 |
Crash Barrier in (m) |
950.00 | 950.00 |
13 |
Road Furniture in (No) |
60.00 | 60.00 |
14 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 1.00 |
15 |
Quality in (%) |
89.25 | |