1 |
Expenditure in (Rs.) |
86700000.00 | 86700000.00 |
2 |
Hill side Cutting & Slip clearence in (KM) |
5.00 | 5.00 |
3 |
R/Wall, B/ Wall Type Protection works in (m) |
380.00 | 380.00 |
4 |
GSB/RBI/G-1 in (KM) |
1.14 | 1.14 |
5 |
G-2 in (KM) |
1.14 | 1.14 |
6 |
G-3 in (KM) |
1.77 | 1.77 |
7 |
PC/CC i/c Prime Coat, Tack Coat in (KM) |
3.21 | 3.21 |
8 |
BM i/c Prime Coat, Tack Coat in (KM) |
6.58 | 6.58 |
9 |
SDBC i/c Tackcoat in (KM) |
11.28 | 11.28 |
10 |
Cause Way in (No) |
3.00 | 3.00 |
11 |
Culverts/Scupper in (No) |
3.00 | 3.00 |
12 |
longitudinal Drain in (m) |
13450.00 | 13450.00 |
13 |
Crash Barrier in (m) |
3980.00 | 3980.00 |
14 |
Parapet in (No) |
65.00 | 65.00 |
15 |
Road Furniture in (No) |
72.00 | 72.00 |
16 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 1.00 |
17 |
Quality in (%) |
91.19 | |