1 |
Expenditure in (Rs.) |
53000000.00 | 53000065.00 |
2 |
Hill side Cutting & Slip clearence in (KM) |
8.00 | 8.00 |
3 |
R/Wall, B/ Wall Type Protection works in (m) |
460.00 | 460.00 |
4 |
GSB/RBI/G-1 in (KM) |
0.20 | 0.20 |
5 |
G-2 in (KM) |
1.60 | 1.60 |
6 |
G-3 in (KM) |
6.00 | 6.00 |
7 |
PC/CC i/c Prime Coat, Tack Coat in (KM) |
0.67 | 0.67 |
8 |
BM i/c Prime Coat, Tack Coat in (KM) |
10.37 | 10.37 |
9 |
SDBC i/c Tackcoat in (KM) |
10.37 | 10.37 |
10 |
Cause Way in (No) |
7.00 | 7.00 |
11 |
Culverts/Scupper in (No) |
8.00 | 8.00 |
12 |
longitudinal Drain in (m) |
9100.00 | 9100.00 |
13 |
Crash Barrier in (m) |
2820.00 | 2820.00 |
14 |
Parapet in (No) |
150.00 | 150.00 |
15 |
Road Furniture in (No) |
46.00 | 46.00 |
16 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 1.00 |
17 |
Quality in (%) |
91.59 | |