Reconstruction of Internal road of Bageshwar Nagar Palika
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 73950000.0069498177.00
2 R/Wall, B/ Wall Type Protection works in (m) 500.00500.00
3 GSB/RBI/G-1 in (KM) 3.903.90
4 G-2 in (KM) 3.903.90
5 G-3 in (KM) 3.903.90
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 0.300.30
7 BM i/c Prime Coat, Tack Coat in (KM) 7.867.86
8 SDBC i/c Tackcoat in (KM) 9.689.68
9 longitudinal Drain in (m) 4500.004500.00
10 Crash Barrier in (m) 1200.001200.00
11 Road Furniture in (No) 1850.001850.00
12 Quality in (%) 90