Progress Details Report

Seraghat-Udiyaribend
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 11160000.008067663.00
2 Hill side Cutting & Slip clearence in (KM) 0.200.17
3 R/Wall, B/ Wall Type Protection works in (m) 200.00171.00
4 G-3 in (KM) 0.350.00
5 Cause Way in (No) 1.001.00
6 Culverts/Scupper in (No) 2.002.00
7 Quality in (%) 91.67