Internal Motor Road of Nagar Palika Pauri (Chronic Slip Zone)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 39430000.0036029803.00
2 R/Wall, B/ Wall Type Protection works in (m) 200.00107.00
3 G-2 in (KM) 0.300.30
4 G-3 in (KM) 0.600.60
5 PC/CC i/c Prime Coat, Tack Coat in (KM) 2.910.00
6 BM i/c Prime Coat, Tack Coat in (KM) 2.652.65
7 SDBC i/c Tackcoat in (KM) 2.652.65
8 Cause Way in (No) 2.000.00
9 Culverts/Scupper in (No) 1.000.00
10 longitudinal Drain in (m) 2900.00700.00
11 Crash Barrier in (m) 550.00550.00
12 Parapet in (No) 105.000.00
13 Road Furniture in (No) 614.00150.00
14 Other Allied Works & Finishing Work in (Job) 2.000.00
15 Quality in (%) 87.88