S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 86695000.0086495909.21
2 Hill side Cutting & Slip clearence in (KM) 0.380.38
3 R/Wall, B/ Wall Type Protection works in (m) 1143.001143.00
4 GSB/RBI/G-1 in (KM) 0.490.49
5 G-2 in (KM) 0.860.86
6 G-3 in (KM) 1.411.41
7 BM i/c Prime Coat, Tack Coat in (KM) 13.5513.55
8 SDBC i/c Tackcoat in (KM) 13.5513.55
9 Cause Way in (No) 2.002.00
10 Culverts/Scupper in (No) 1.001.00
11 longitudinal Drain in (m) 12980.0012950.00
12 Crash Barrier in (m) 1445.001432.00
13 Road Furniture in (No) 1295.001295.00
14 Other Allied Works & Finishing Work in (Job) 1.000.00
15 Quality in (%) 85.33