1 |
Expenditure in (Rs.) |
39213000.00 | 39391441.00 |
2 |
Hill side Cutting & Slip clearence in (KM) |
0.58 | 0.58 |
3 |
R/Wall, B/ Wall Type Protection works in (m) |
1013.00 | 1013.00 |
4 |
GSB/RBI/G-1 in (KM) |
0.22 | 0.22 |
5 |
G-2 in (KM) |
0.33 | 0.33 |
6 |
G-3 in (KM) |
1.81 | 1.81 |
7 |
PC/CC i/c Prime Coat, Tack Coat in (KM) |
7.00 | 7.00 |
8 |
BM i/c Prime Coat, Tack Coat in (KM) |
3.50 | 3.50 |
9 |
SDBC i/c Tackcoat in (KM) |
14.00 | 14.00 |
10 |
Cause Way in (No) |
4.00 | 4.00 |
11 |
Culverts/Scupper in (No) |
4.00 | 4.00 |
12 |
longitudinal Drain in (m) |
27550.00 | 27550.00 |
13 |
Crash Barrier in (m) |
700.00 | 700.00 |
14 |
Parapet in (No) |
16.00 | 0.00 |
15 |
Road Furniture in (No) |
457.00 | 457.00 |
16 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 0.00 |
17 |
Quality in (%) |
88.82 | |