Menu

Progress Details Report

Internal MR Of Canal Road To Sahastradhara Road In Raipur Block
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 19928000.0015705179.00
2 Hill side Cutting & Slip clearence in (KM) 0.240.24
3 R/Wall, B/ Wall Type Protection works in (m) 25.0025.00
4 GSB/RBI/G-1 in (KM) 0.730.73
5 G-2 in (KM) 0.730.73
6 G-3 in (KM) 0.700.70
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 0.360.36
8 BM i/c Prime Coat, Tack Coat in (KM) 0.200.20
9 SDBC i/c Tackcoat in (KM) 0.770.77
10 Culverts/Scupper in (No) 2.002.00
11 longitudinal Drain in (m) 2420.002420.00
12 Crash Barrier in (m) 100.00100.00
13 Parapet in (No) 200.0033.00
14 Road Furniture in (No) 251.00251.00
15 Other Allied Works & Finishing Work in (Job) 24.0024.00
16 Quality in (%) Not Rated Yet