Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 57885000.0048541139.00
2 Hill side Cutting & Slip clearence in (KM) 1.211.21
3 R/Wall, B/ Wall Type Protection works in (m) 2180.002180.00
4 G-2 in (KM) 0.300.00
5 G-3 in (KM) 0.030.03
6 BM i/c Prime Coat, Tack Coat in (KM) 3.443.44
7 SDBC i/c Tackcoat in (KM) 3.443.44
8 Cause Way in (No) 9.002.00
9 longitudinal Drain in (m) 2500.002500.00
10 Crash Barrier in (m) 280.00280.00
11 Parapet in (No) 360.00246.00
12 Road Furniture in (No) 1166.001046.00
13 Quality in (%) 89.88