Progress Details Report

Ghamiyala-Budakedar Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 28144000.0025198720.00
2 Hill side Cutting & Slip clearence in (KM) 0.800.80
3 R/Wall, B/ Wall Type Protection works in (m) 170.00170.00
4 G-2 in (KM) 1.501.50
5 G-3 in (KM) 1.501.50
6 BM i/c Prime Coat, Tack Coat in (KM) 1.901.90
7 SDBC i/c Tackcoat in (KM) 4.074.07
8 Cause Way in (No) 4.003.00
9 longitudinal Drain in (m) 1200.00710.00
10 Crash Barrier in (m) 400.000.00
11 Parapet in (No) 190.00167.00
12 Road Furniture in (No) 1113.001000.00
13 Quality in (%) 93.21