Progress Details Report

Pilkhi-Gadoliya Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 37100000.0043821354.00
2 Hill side Cutting & Slip clearence in (KM) 0.490.49
3 R/Wall, B/ Wall Type Protection works in (m) 1207.001207.00
4 GSB/RBI/G-1 in (KM) 0.470.47
5 G-2 in (KM) 0.610.61
6 G-3 in (KM) 2.082.08
7 BM i/c Prime Coat, Tack Coat in (KM) 2.082.08
8 SDBC i/c Tackcoat in (KM) 9.829.82
9 Cause Way in (No) 3.003.00
10 Culverts/Scupper in (No) 12.0012.00
11 Crash Barrier in (m) 750.00750.00
12 Parapet in (No) 480.00480.00
13 Road Furniture in (No) 1197.001197.00
14 Quality in (%) 90