Progress Details Report

Pokhri-Gopeshwar Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 49372000.0044341078.00
2 Hill side Cutting & Slip clearence in (KM) 0.250.00
3 R/Wall, B/ Wall Type Protection works in (m) 3746.001100.00
4 GSB/RBI/G-1 in (KM) 0.030.02
5 G-2 in (KM) 0.070.06
6 G-3 in (KM) 0.780.78
7 BM i/c Prime Coat, Tack Coat in (KM) 0.840.84
8 SDBC i/c Tackcoat in (KM) 3.302.62
9 Cause Way in (No) 23.000.00
10 Culverts/Scupper in (No) 79.0060.00
11 longitudinal Drain in (m) 2800.002800.00
12 Crash Barrier in (m) 585.00585.00
13 Road Furniture in (No) 1148.00700.00
14 Other Allied Works & Finishing Work in (Job) 3.000.00
15 Quality in (%) 94.57