Progress Details Report

Tharali-Dewal-Mundoli
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 220337000.00202233792.50
2 R/Wall, B/ Wall Type Protection works in (m) 4610.004600.00
3 GSB/RBI/G-1 in (KM) 2.372.15
4 G-2 in (KM) 2.372.15
5 G-3 in (KM) 2.372.15
6 Culverts/Scupper in (No) 26.0018.00
7 longitudinal Drain in (m) 37695.0022000.00
8 Crash Barrier in (m) 6000.006000.00
9 Parapet in (No) 3700.00120.00
10 Road Furniture in (No) 1382.00900.00
11 Other Allied Works & Finishing Work in (Job) 8.000.00
12 Quality in (%) 94.13