Progress Details Report

Rudraprayag-pokhari-Karanprayag
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 11200000.005972711.30
2 Hill side Cutting & Slip clearence in (KM) 0.000.00
3 R/Wall, B/ Wall Type Protection works in (m) 281.00130.00
4 GSB/RBI/G-1 in (KM) 0.000.00
5 G-2 in (KM) 0.000.00
6 G-3 in (KM) 0.320.11
7 BM i/c Prime Coat, Tack Coat in (KM) 0.480.43
8 SDBC i/c Tackcoat in (KM) 2.792.79
9 Cause Way in (No) 0.000.00
10 Culverts/Scupper in (No) 0.000.00
11 longitudinal Drain in (m) 1750.000.00
12 Crash Barrier in (m) 400.00400.00
13 Parapet in (No) 0.000.00
14 Road Furniture in (No) 95.000.00
15 Quality in (%) 90