Progress Details Report

Nandprayag- Ghat
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 21100000.0037026278.30
2 Hill side Cutting & Slip clearence in (KM) 0.470.35
3 R/Wall, B/ Wall Type Protection works in (m) 1210.00607.00
4 GSB/RBI/G-1 in (KM) 0.200.20
5 G-2 in (KM) 0.590.43
6 G-3 in (KM) 1.030.90
7 BM i/c Prime Coat, Tack Coat in (KM) 1.501.50
8 SDBC i/c Tackcoat in (KM) 6.586.58
9 Cause Way in (No) 10.007.00
10 Culverts/Scupper in (No) 0.000.00
11 longitudinal Drain in (m) 18500.007850.00
12 Crash Barrier in (m) 600.00600.00
13 Parapet in (No) 190.0090.00
14 Road Furniture in (No) 209.0074.00
15 Quality in (%) 90