Progress Details Report

Tyuni-Mori-Purola-Naugaon
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 84265000.0072610919.00
2 Hill side Cutting & Slip clearence in (KM) 0.450.45
3 R/Wall, B/ Wall Type Protection works in (m) 600.00600.00
4 GSB/RBI/G-1 in (KM) 0.130.13
5 G-2 in (KM) 0.750.75
6 G-3 in (KM) 0.750.75
7 BM i/c Prime Coat, Tack Coat in (KM) 1.501.50
8 SDBC i/c Tackcoat in (KM) 32.0032.00
9 longitudinal Drain in (m) 3250.003250.00
10 Crash Barrier in (m) 500.00500.00
11 Parapet in (No) 1250.001250.00
12 Road Furniture in (No) 4020.004020.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 92.07