Menu

Progress Details Report

Bridge near Km-2 of Kund Kotla Motor Road at Kund Khad
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 27001000.0025207585.76
2 Other Allied Works & Finishing Work in (Job) 1.001.00
3 Foundation RHS in (Job) 1.001.00
4 Foundation LHS in (Job) 1.001.00
5 Abutment Superstructure RHS in (Job) 1.001.00
6 Abutment Superstructure LHS in (Job) 1.001.00
7 Fixing of chequered Plate/RCC Deck in (sqm) 1.001.00
8 Steel Railing/crush barrier in (m) 1.001.00
9 Approach Ramp /path in (m) 1.001.00
10 Protection Work in (Job) 1.001.00
11 Errection Work in (Job) 1.001.00
12 Fabrication Work in (job) 1.001.00
13 Fixing Bearing/Slab Casting in (job) 4.004.00
14 Quality in (%) 93.14