Progress Details Report

Suspension Bridge Between Village Tiwari Goan and Village Ghangreti over Kosi River
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 138294000.00138834357.00
2 Other Allied Works & Finishing Work in (Job) 1.000.00
3 Group of Pile in (No) 1.001.00
4 Foundation RHS in (Job) 1.001.00
5 Foundation LHS in (Job) 1.001.00
6 Steel Railing/crush barrier in (m) 320.000.00
7 Approach Ramp /path in (m) 200.000.00
8 Errection Work in (Job) 1.000.00
9 Gabion work in (m) 100.000.00
10 Fabrication Work in (job) 1.000.00
11 Abutment Substructure RHS in (Job) 1.001.00
12 Abutment Substructure LHS in (Job) 1.001.00
13 Back Wall/ Approach slab in (job) 1.000.00
14 Quality in (%) 94.7
15 Admin Block in (Job) 0.000.00