1 |
Expenditure in (Rs.) |
49144000.00 | 13553325.00 |
2 |
Env. Man & Moni Plan in (Job) |
1.00 | 0.30 |
3 |
Other Allied Works & Finishing Work in (Job) |
4.00 | 2.00 |
4 |
Foundation RHS in (Job) |
1.00 | 0.00 |
5 |
Foundation LHS in (Job) |
1.00 | 1.00 |
6 |
Abutment Superstructure RHS in (Job) |
1.00 | 0.00 |
7 |
Abutment Superstructure LHS in (Job) |
1.00 | 0.00 |
8 |
Fixing of chequered Plate/RCC Deck in (sqm) |
1.00 | 0.00 |
9 |
Steel Railing/crush barrier in (m) |
142.40 | 0.00 |
10 |
Approach Ramp /path in (m) |
150.00 | 0.00 |
11 |
Protection Work in (Job) |
1.00 | 0.00 |
12 |
Errection Work in (Job) |
1.00 | 0.00 |
13 |
Fabrication Work in (job) |
1.00 | 0.50 |
14 |
Abutment Substructure RHS in (Job) |
1.00 | 0.00 |
15 |
Abutment Substructure LHS in (Job) |
1.00 | 0.00 |
16 |
Quality in (%) |
90 | |