Menu

Progress Details Report

Steel Girder Bridle Bridge over Jalkur River on Sem Bhardar Gajna Bridle Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 16357000.0013353819.12
2 Other Allied Works & Finishing Work in (Job) 1.000.85
3 Foundation RHS in (Job) 1.001.00
4 Foundation LHS in (Job) 1.001.00
5 Abutment Superstructure RHS in (Job) 1.001.00
6 Abutment Superstructure LHS in (Job) 1.001.00
7 Fixing of chequered Plate/RCC Deck in (sqm) 88.800.00
8 Steel Railing/crush barrier in (m) 1.000.00
9 Approach Ramp /path in (m) 1.001.00
10 Protection Work in (Job) 1.001.00
11 Errection Work in (Job) 1.000.10
12 Fabrication Work in (job) 1.001.00
13 Quality in (%) 87.48