Menu

Progress Details Report

RCC Bridge at Rathuadab over Mandal River
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 184550000.00189768398.10
2 Other Allied Works & Finishing Work in (Job) 1.000.75
3 Pile Cap in (No) 4.004.00
4 Group of Pile in (No) 4.004.00
5 Abutment Superstructure RHS in (Job) 1.001.00
6 Abutment Superstructure LHS in (Job) 1.001.00
7 Approach Ramp /path in (m) 800.000.00
8 Fixing Bearing/Slab Casting in (job) 5.005.00
9 Well-Abutments/Pier/Shafts/Caps in (job) 4.004.00
10 PSC girder & Diaphragms in (No) 5.005.00
11 Quality in (%) 98.32