1 |
Expenditure in (Rs.) |
57329000.00 | 56275408.00 |
2 |
Hill side Cutting & Slip clearence in (KM) |
0.10 | 0.10 |
3 |
R/Wall, B/ Wall Type Protection works in (m) |
200.00 | 50.00 |
4 |
PC/CC i/c Prime Coat, Tack Coat in (KM) |
0.10 | 0.10 |
5 |
Crash Barrier in (m) |
110.00 | 0.00 |
6 |
Road Furniture in (No) |
2.00 | 2.00 |
7 |
Env. Man & Moni Plan in (Job) |
1.00 | 1.00 |
8 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 1.00 |
9 |
Foundation RHS in (Job) |
1.00 | 1.00 |
10 |
Foundation LHS in (Job) |
1.00 | 1.00 |
11 |
Abutment Superstructure RHS in (Job) |
1.00 | 1.00 |
12 |
Abutment Superstructure LHS in (Job) |
1.00 | 1.00 |
13 |
Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) |
1.00 | 1.00 |
14 |
Steel Railing/crush barrier in (m) |
120.00 | 0.00 |
15 |
Approach Ramp /path in (m) |
100.00 | 100.00 |
16 |
Protection Work in (Job) |
1.00 | 0.20 |
17 |
Errection Work in (Job) |
1.00 | 1.00 |
18 |
Gabion work in (m) |
720.00 | 136.50 |
19 |
PCC in Foundation in (cum) |
25.16 | 25.16 |
20 |
Fabrication Work in (job) |
1.00 | 1.00 |
21 |
Fixing Bearing/Slab Casting in (job) |
6.00 | 6.00 |
22 |
Wearing Coat in (Cum) |
14.90 | 14.90 |
23 |
Quality in (%) |
94.48 | |