Progress Details Report

Sukhi River
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 110876000.00110861194.07
2 Stressing & Grouting in (Job) 120.00120.00
3 Env. Man & Moni Plan in (Job) 45.0045.00
4 Other Allied Works & Finishing Work in (Job) 12.0012.00
5 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 6.006.00
6 Steel Railing/crush barrier in (m) 360.00360.00
7 Approach Ramp /path in (m) 850.00850.00
8 Protection Work in (Job) 4.004.00
9 Fixing Bearing/Slab Casting in (job) 48.0048.00
10 Back Wall/ Approach slab in (job) 2.002.00
11 Providing and laying cutting in (mt) 6.786.78
12 Concreting Well Curb and Steaming in (job) 7.007.00
13 Well Sinking in (rmt) 149.00149.00
14 Bottom Plug/Top Plug in (Cum) 329.00329.00
15 Sand Filling in (Cum) 2087.522087.52
16 Well-Abutments/Pier/Shafts/Caps in (job) 7.007.00
17 PSC girder & Diaphragms in (No) 24.0024.00
18 Wearing Coat in (Cum) 101.75101.75
19 Quality in (%) 92.79