Progress Details Report

120m span bridle Suspension Bridge at Piplogi
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 86772000.0080156665.00
2 Other Allied Works & Finishing Work in (Job) 1.001.00
3 Foundation RHS in (Job) 1.001.00
4 Foundation LHS in (Job) 1.001.00
5 Abutment Superstructure RHS in (Job) 1.001.00
6 Abutment Superstructure LHS in (Job) 1.001.00
7 Anchor Block Main Cable Reinforcement (3-4 Times) in (job) 1.001.00
8 Anchor Block for Wind Cable: Reinforcement, Lewis in (job) 1.001.00
9 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 2.002.00
10 Fixing of Saddle pulley along with Rib plate and in (no) 4.004.00
11 Fixing Suspenders to Main cable with clamps and Ha in (no) 154.00154.00
12 Stretching Wind Guy cable, Fixing wind Ties with in (m) 574.00574.00
13 Fixing longitudinal Stringers/girders in (m) 120.00120.00
14 Fixing of chequered Plate/RCC Deck in (sqm) 306.00306.00
15 Steel Railing/crush barrier in (m) 240.00240.00
16 Approach Ramp /path in (m) 100.00100.00
17 Protection Work in (Job) 1.001.00
18 Errection Work in (Job) 1.001.00
19 Gabion work in (m) 2400.002400.00
20 PCC in Foundation in (cum) 261.00261.00
21 Excavation in soil in (cum) 5734.005734.00
22 Fabrication Work in (job) 1.001.00
23 Quality in (%) 91.97