Menu

Progress Details Report

Bridge Over Bhagirathi River at Chamkot Village
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 53319000.0053573902.92
2 R/Wall, B/ Wall Type Protection works in (m) 1.001.00
3 Other Allied Works & Finishing Work in (Job) 1.000.65
4 Foundation RHS in (Job) 1.001.00
5 Foundation LHS in (Job) 1.001.00
6 Abutment Superstructure RHS in (Job) 1.001.00
7 Abutment Superstructure LHS in (Job) 1.001.00
8 Steel Railing/crush barrier in (m) 170.000.00
9 Approach Ramp /path in (m) 8400.008400.00
10 Protection Work in (Job) 1.001.00
11 Errection Work in (Job) 1.000.00
12 Gabion work in (m) 300.00300.00
13 Fabrication Work in (job) 211.60211.60
14 Fixing Bearing/Slab Casting in (job) 1.000.00
15 Back Wall/ Approach slab in (job) 1.000.00
16 Quality in (%) 90