1 |
Expenditure in (Rs.) |
89910000.00 | 98269779.28 |
2 |
Other Allied Works & Finishing Work in (Job) |
1.00 | 0.50 |
3 |
Foundation RHS in (Job) |
1.00 | 0.85 |
4 |
Foundation LHS in (Job) |
1.00 | 1.00 |
5 |
Abutment Superstructure RHS in (Job) |
1.00 | 0.00 |
6 |
Abutment Superstructure LHS in (Job) |
1.00 | 0.50 |
7 |
Anchor Block Main Cable Reinforcement (3-4 Times) in (job) |
1.00 | 0.70 |
8 |
Anchor Block for Wind Cable: Reinforcement, Lewis in (job) |
1.00 | 0.00 |
9 |
Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) |
2.00 | 0.00 |
10 |
Fixing of Saddle pulley along with Rib plate and in (no) |
4.00 | 0.00 |
11 |
Fixing Suspenders to Main cable with clamps and Ha in (no) |
114.00 | 0.00 |
12 |
Stretching Wind Guy cable, Fixing wind Ties with in (m) |
1528.00 | 0.00 |
13 |
Fixing longitudinal Stringers/girders in (m) |
270.00 | 0.00 |
14 |
Fixing of chequered Plate/RCC Deck in (sqm) |
170.00 | 0.00 |
15 |
Steel Railing/crush barrier in (m) |
180.00 | 0.00 |
16 |
Approach Ramp /path in (m) |
100.00 | 30.00 |
17 |
Protection Work in (Job) |
1.00 | 0.55 |
18 |
Errection Work in (Job) |
54.20 | 0.00 |
19 |
Gabion work in (m) |
960.00 | 400.00 |
20 |
PCC in Foundation in (cum) |
88.70 | 50.93 |
21 |
Excavation in soil in (cum) |
5732.40 | 5732.40 |
22 |
Fabrication Work in (job) |
54.20 | 54.20 |
23 |
Quality in (%) |
90.47 | |