Progress Details Report

Bridge in KM-3 of Sisaldi Satpuli MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 46391000.0046390752.00
2 Hill side Cutting & Slip clearence in (KM) 0.110.11
3 R/Wall, B/ Wall Type Protection works in (m) 70.0070.00
4 PC/CC i/c Prime Coat, Tack Coat in (KM) 0.150.15
5 longitudinal Drain in (m) 105.00105.00
6 Crash Barrier in (m) 94.0094.00
7 Road Furniture in (No) 4.004.00
8 Env. Man & Moni Plan in (Job) 1.001.00
9 Other Allied Works & Finishing Work in (Job) 10.0010.00
10 Foundation RHS in (Job) 1.001.00
11 Foundation LHS in (Job) 1.001.00
12 Abutment Superstructure RHS in (Job) 1.001.00
13 Abutment Superstructure LHS in (Job) 1.001.00
14 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 1.001.00
15 Steel Railing/crush barrier in (m) 0.000.00
16 Approach Ramp /path in (m) 105.00105.00
17 Protection Work in (Job) 1.001.00
18 Errection Work in (Job) 1.001.00
19 Gabion work in (m) 150.00150.00
20 PCC in Foundation in (cum) 13.6213.62
21 Fabrication Work in (job) 1.001.00
22 Fixing Bearing/Slab Casting in (job) 6.006.00
23 Wearing Coat in (Cum) 9.889.88
24 Quality in (%) 98.98