Progress Details Report

Bridge on KM-7 of Agrakhal Kusraila MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 18178000.0018177857.00
2 Other Allied Works & Finishing Work in (Job) 1.001.00
3 Foundation RHS in (Job) 1.001.00
4 Foundation LHS in (Job) 1.001.00
5 Steel Railing/crush barrier in (m) 110.00110.00
6 Approach Ramp /path in (m) 95.0095.00
7 Protection Work in (Job) 1.001.00
8 Errection Work in (Job) 1.001.00
9 Fabrication Work in (job) 1.001.00
10 Abutment Substructure RHS in (Job) 1.001.00
11 Abutment Substructure LHS in (Job) 1.001.00
12 Fixing Bearing/Slab Casting in (job) 1.001.00
13 Wearing Coat in (Cum) 12.3112.31
14 Quality in (%) 90.1