Progress Details Report

Khutani Bhawali Dhanachuli Okhalkanda Khansyu Patlot Bridge in KM-85
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 60120000.0048965899.00
2 Env. Man & Moni Plan in (Job) 25.0010.00
3 Other Allied Works & Finishing Work in (Job) 1.000.25
4 Foundation RHS in (Job) 1.001.00
5 Foundation LHS in (Job) 1.001.00
6 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 1.000.00
7 Approach Ramp /path in (m) 132.0030.00
8 Protection Work in (Job) 2.001.00
9 Errection Work in (Job) 1.001.00
10 Fabrication Work in (job) 1.001.00
11 Abutment Substructure RHS in (Job) 1.001.00
12 Abutment Substructure LHS in (Job) 1.001.00
13 Quality in (%) 91.77