Progress Details Report

Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 65658000.0065600250.00
2 R/Wall, B/ Wall Type Protection works in (m) 140.00140.00
3 Env. Man & Moni Plan in (Job) 28.0028.00
4 Other Allied Works & Finishing Work in (Job) 1.001.00
5 Foundation RHS in (Job) 1.001.00
6 Foundation LHS in (Job) 1.001.00
7 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 1.001.00
8 Steel Railing/crush barrier in (m) 120.00120.00
9 Approach Ramp /path in (m) 100.00100.00
10 Errection Work in (Job) 190.86190.86
11 Gabion work in (m) 186.00186.00
12 PCC in Foundation in (cum) 29.9029.90
13 Excavation in soil in (cum) 6688.326688.32
14 Fabrication Work in (job) 184.80184.80
15 Abutment Substructure RHS in (Job) 1.001.00
16 Fixing Bearing/Slab Casting in (job) 6.006.00
17 Back Wall/ Approach slab in (job) 2.002.00
18 Quality in (%) 94.23
19 Wearing Coat in (Cum) 23.4023.40