Progress Details Report

Tachla Naur Slope Motor Road KM-1
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 54572000.0054552945.00
2 R/Wall, B/ Wall Type Protection works in (m) 221.00221.00
3 Stressing & Grouting in (Job) 1.001.00
4 Env. Man & Moni Plan in (Job) 1.001.00
5 Other Allied Works & Finishing Work in (Job) 1.001.00
6 Approach Ramp /path in (m) 150.00150.00
7 Anchors in (m) 8739.008739.00
8 Hydroseeding,3-D Net, High tensile Rolled Cable Net in (sqm) 8250.008250.00
9 Gabion work in (m) 150.00150.00
10 Quality in (%) 92.32