Progress Details Report

Road protection WORK of jajalgaja mr KM-4
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 23702000.0023701793.00
2 Hill side Cutting & Slip clearence in (KM) 0.090.09
3 R/Wall, B/ Wall Type Protection works in (m) 131.60131.60
4 Stressing & Grouting in (Job) 1.001.00
5 Env. Man & Moni Plan in (Job) 1.001.00
6 Other Allied Works & Finishing Work in (Job) 1.001.00
7 Approach Ramp /path in (m) 130.00130.00
8 Anchors in (m) 3100.003100.00
9 Hydroseeding,3-D Net, High tensile Rolled Cable Net in (sqm) 7730.167730.16
10 Gabion work in (m) 24.0024.00
11 PCC in Foundation in (cum) 50.8050.80
12 Excavation in soil in (cum) 864.00864.00
13 Retrofitting in (job) 1.001.00
14 Quality in (%) 90.39