Progress Details Report

Shri Purnagiri Temple Area in Tanakpur Slope MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 41863000.0043140009.00
2 Env. Man & Moni Plan in (Job) 26.008.00
3 Other Allied Works & Finishing Work in (Job) 3.001.00
4 Steel Railing/crush barrier in (m) 860.000.00
5 Errection Work in (Job) 100.000.00
6 Anchors in (m) 3172.001920.00
7 Hydroseeding,3-D Net, High tensile Rolled Cable Net in (sqm) 1980.000.00
8 PCC in Foundation in (cum) 395.000.00
9 Excavation in soil in (cum) 124.000.00
10 Reinforcement work in (mt) 210.000.00
11 Sand Filling in (Cum) 168.200.00
12 Wearing Coat in (Cum) 142.500.00
13 Quality in (%) 95.01