Progress Details Report

Guptkashi - Jakholi Slope MR at Km No.17
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 34907000.000.00
2 G-2 in (KM) 0.110.00
3 G-3 in (KM) 0.110.00
4 PC/CC i/c Prime Coat, Tack Coat in (KM) 0.110.00
5 Other Allied Works & Finishing Work in (Job) 1.000.10
6 Gravity Bench Wall in (m) 90.005.00
7 Anchors in (m) 1418.500.00
8 Micropile in (m) 1050.000.00
9 Gabion work in (m) 1618.670.00
10 Quality in (%) 90