Progress Details Report

Bridge at KM 15 of Balmara Syalde Kedar MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 137216000.00137811499.00
2 Env. Man & Moni Plan in (Job) 1.001.00
3 Other Allied Works & Finishing Work in (Job) 1.001.00
4 Foundation RHS in (Job) 1.001.00
5 Foundation LHS in (Job) 1.001.00
6 Abutment Superstructure RHS in (Job) 0.000.00
7 Abutment Superstructure LHS in (Job) 0.000.00
8 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 1.001.00
9 Fixing of chequered Plate/RCC Deck in (sqm) 173.00173.00
10 Steel Railing/crush barrier in (m) 1.000.00
11 Approach Ramp /path in (m) 2.002.00
12 Protection Work in (Job) 1.001.00
13 Errection Work in (Job) 1.001.00
14 Fabrication Work in (job) 1.001.00
15 Abutment Substructure RHS in (Job) 1.001.00
16 Abutment Substructure LHS in (Job) 1.001.00
17 Quality in (%) 95