Menu

Progress Details Report

Bridge at Ruch Mahadev Kotimaheshwar Mandir Bridle Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 1170000.001169570.00
2 Other Allied Works & Finishing Work in (Job) 1.001.00
3 Foundation RHS in (Job) 1.000.50
4 Foundation LHS in (Job) 1.001.00
5 Abutment Superstructure RHS in (Job) 0.000.00
6 Abutment Superstructure LHS in (Job) 1.000.10
7 Fixing of chequered Plate/RCC Deck in (sqm) 0.000.00
8 Steel Railing/crush barrier in (m) 0.000.00
9 Approach Ramp /path in (m) 0.000.00
10 Protection Work in (Job) 0.000.00
11 Errection Work in (Job) 0.000.00
12 Quality in (%) 90