Progress Details Report

Bridge over Alaknanda river at Aarudi- Paturdi
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 116198000.00108844811.00
2 Foundation RHS in (Job) 1.001.00
3 Foundation LHS in (Job) 1.001.00
4 Abutment Superstructure RHS in (Job) 1.001.00
5 Abutment Superstructure LHS in (Job) 1.001.00
6 Trestle Erection and Bracing of Trestle Tower LHS in (job) 1.001.00
7 Anchor Block Main Cable Reinforcement (3-4 Times) in (job) 1.001.00
8 Anchor Block for Wind Cable: Reinforcement, Lewis in (job) 2.002.00
9 Deck Cable laying, stretching and Fixing Transoms/Deck Slab in (no) 2.002.00
10 Fixing of Saddle pulley along with Rib plate and in (no) 4.004.00
11 Main Cable Laying and Stretching in (no) 1148.001148.00
12 Fixing Suspenders to Main cable with clamps and Ha in (no) 90.0090.00
13 Stretching Wind Guy cable, Fixing wind Ties with in (m) 90.0090.00
14 Fixing longitudinal Stringers/girders in (m) 34.7034.70
15 Fixing of chequered Plate/RCC Deck in (sqm) 17.2317.23
16 Steel Railing/crush barrier in (m) 306.00306.00
17 Approach Ramp /path in (m) 126.00126.00
18 Quality in (%) 90