Progress Details Report

Newgaon Sari Shrikalkhal Motor road phase 2
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 59669000.0059208932.00
2 Hill side Cutting & Slip clearence in (KM) 9.009.00
3 R/Wall, B/ Wall Type Protection works in (m) 1400.001400.00
4 GSB/RBI/G-1 in (KM) 9.009.00
5 G-2 in (KM) 9.009.00
6 G-3 in (KM) 9.009.00
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 9.729.72
8 Cause Way in (No) 0.000.00
9 Culverts/Scupper in (No) 26.0026.00
10 longitudinal Drain in (m) 9500.009500.00
11 Crash Barrier in (m) 300.00300.00
12 Parapet in (No) 350.00350.00
13 Road Furniture in (No) 57.0057.00
14 Env. Man & Moni Plan in (Job) 1.001.00
15 Quality in (%) 87.78