Progress Details Report

Pipli to gawana Motor road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 15247000.0015966865.50
2 R/Wall, B/ Wall Type Protection works in (m) 620.00620.00
3 GSB/RBI/G-1 in (KM) 2.602.60
4 G-2 in (KM) 2.602.60
5 G-3 in (KM) 2.602.60
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 2.802.80
7 Culverts/Scupper in (No) 16.0016.00
8 longitudinal Drain in (m) 2800.002800.00
9 Parapet in (No) 130.00130.00
10 Road Furniture in (No) 88.0088.00
11 Quality in (%) 89.79