Menu

Progress Details Report

Ranari to Danda Majaf MR
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 34073000.0037336826.29
2 Hill side Cutting & Slip clearence in (KM) 4.004.00
3 R/Wall, B/ Wall Type Protection works in (m) 2119.002119.00
4 GSB/RBI/G-1 in (KM) 4.604.60
5 G-2 in (KM) 4.604.60
6 G-3 in (KM) 4.604.60
7 PC/CC i/c Prime Coat, Tack Coat in (KM) 4.604.60
8 Cause Way in (No) 1.001.00
9 Culverts/Scupper in (No) 15.0015.00
10 longitudinal Drain in (m) 4500.004500.00
11 Crash Barrier in (m) 0.000.00
12 Road Furniture in (No) 12.0012.00
13 Quality in (%) 80.8