Progress Details Report

Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 82394000.0034896259.52
2 Hill side Cutting & Slip clearence in (KM) 10.009.60
3 R/Wall, B/ Wall Type Protection works in (m) 1384.001170.00
4 G-2 in (KM) 14.2513.35
5 G-3 in (KM) 8.415.90
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 10.000.37
7 Cause Way in (No) 4.003.00
8 Culverts/Scupper in (No) 28.0020.00
9 longitudinal Drain in (m) 9955.005920.00
10 Crash Barrier in (m) 1450.000.00
11 Parapet in (No) 950.00500.00
12 Road Furniture in (No) 594.000.00
13 Other Allied Works & Finishing Work in (Job) 1.000.40
14 Quality in (%) 95.68