Progress Details Report

Khujeer bend to Chauki Barsil Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 7540000.009348123.88
2 Hill side Cutting & Slip clearence in (KM) 1.001.00
3 R/Wall, B/ Wall Type Protection works in (m) 140.00140.00
4 G-2 in (KM) 2.102.10
5 G-3 in (KM) 1.051.05
6 PC/CC i/c Prime Coat, Tack Coat in (KM) 1.051.05
7 Cause Way in (No) 3.003.00
8 Culverts/Scupper in (No) 2.002.00
9 longitudinal Drain in (m) 980.00980.00
10 Crash Barrier in (m) 100.00100.00
11 Parapet in (No) 35.0035.00
12 Road Furniture in (No) 6.006.00
13 Other Allied Works & Finishing Work in (Job) 1.001.00
14 Quality in (%) 91