Progress Details Report

Nagrasu-Dhanpur-Dandakhal Motor Road
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 106030000.00106806846.00
2 Hill side Cutting & Slip clearence in (KM) 0.680.68
3 R/Wall, B/ Wall Type Protection works in (m) 680.00680.00
4 GSB/RBI/G-1 in (KM) 0.250.25
5 G-2 in (KM) 0.520.52
6 G-3 in (KM) 1.381.38
7 BM i/c Prime Coat, Tack Coat in (KM) 27.6527.65
8 SDBC i/c Tackcoat in (KM) 27.6527.65
9 Cause Way in (No) 7.007.00
10 Culverts/Scupper in (No) 6.006.00
11 longitudinal Drain in (m) 24770.0024770.00
12 Crash Barrier in (m) 1777.001777.00
13 Parapet in (No) 1127.001127.00
14 Road Furniture in (No) 139.00139.00
15 Quality in (%) 88.23